Finance GuideWhere construction finance teams can protect margin

Construction's insolvency numbers aren't improving: Where finance teams can still protect margin

Henry Bewicke Author Profile Headshot
Written byHenry Bewicke
November 11, 2026
Budgeting & Cash Flow5 minutes
Construction insolvency numbers aren't improving where finance teams can still protect margin

For a UK main contractor, the insolvency most likely to cost you this year is a subcontractor's. The pattern is familiar. A subcontractor's application for payment is approved in full, against a valuation made generous because the site wanted the firm to stay. A few weeks later the administrators write.

The direct loss is whatever was paid ahead of the work actually done. The indirect losses follow: the package has to be re-procured at this year's prices, HMRC still wants the monthly CIS return by the 19th and your records of what you paid them for three years after the tax year ends (GOV.UK), and the cost report for that job is weeks behind because the invoices were never coded to it.

None of the forces behind the sector's numbers (materials, wages, late payment, demand) are yours to move. What a finance team does control is the money that leaves the business without being earned.

In this article we'll look at what the insolvency figures actually say, why a credit check and a bigger retention don't cover you, which leaks a finance team can close, and where a spend tool stops.

What the insolvency numbers actually say

The Insolvency Service recorded 3,805 construction insolvencies in England and Wales in the year to June 2026, 17% of all company insolvencies and more than any other sector, though fewer than the year before. Within construction the largest group is specialised construction activities, the trades a main contractor pays: in June alone 173 of 309 construction failures were specialist subcontractors, against 127 builders and developers.

None of the main drivers are things that finance can control. Fabricated structural steel was up 21.2% in the year to August 2026 and the all-work materials index 6.4%, construction output fell in the three months to July, and the Bank of England's agents report tighter funding and projects being delayed (BIST, September 2026).

Late payment costs the economy almost £11bn a year and closes 14,000 businesses on the government's figures, and the ban on retentions it announced in March 2026 is in the Commercial Payments Bill, through the Lords and now with the Commons; consultation respondents backed a 12 to 24-month transition after Royal Assent.

So the firms most likely to fail are the ones you pay. And when one does, your exposure is set by three things you decided: how far ahead of certified work you paid them, whether their last invoice exceeded what you ordered, and whether your records of the payments are complete enough to stand when the subcontractor is no longer there to ask.

Why a credit check and a bigger retention don't cover it

A credit check describes the day it was run. The trades failing in 2026 were passing checks in 2025, and a subcontractor's position moves faster than any agency's data. A bigger retention is the traditional buffer, and the government has chosen to ban retentions outright rather than require them to be ring-fenced, the alternative it consulted on. Pricing a fatter margin into the tender protects you only if nothing leaks after the tender is won.

Four leaks finance can stop

In practice there are four:

1. Money paid ahead of work done, because an application was approved on goodwill rather than a valuation.

2. Money paid above what was ordered, because the invoice was never compared with the order.

3. Money paid to a payee nobody in finance set up, because a site manager added the supplier.

4. Money that was earned but can't be attributed, because the invoice carried no job code and the cost report had to be rebuilt after the fact.

Four controls finance owns

The approach is to put the check at the point of payment rather than in the post-mortem:

1. Pay against orders, so an application above the approved value is an approval event rather than a payment.

2. Pay against what was received or certified, with a goods receipt or valuation behind it.

3. Create suppliers through finance only, so a payee has to exist before it can be paid.

4. Code every line to its job on entry, so the cost report is current when a subcontractor fails rather than reconstructed afterwards.

Where Moss fits, and where it stops

Moss covers those four controls. An invoice that exceeds its purchase order by any amount goes back into approval before it can be paid, with no tolerance band, and for goods the invoice can be matched against a received-quantity note. A new supplier named on a purchase request is not created until finance sets it up when the first invoice arrives, because supplier management stays with the finance team. Project and cost-centre fields can be made mandatory at review, verification and approval, so no invoice or card line moves without its job, and those fields, including custom ones such as a materials element, carry through to the accounting export.

While Moss doesn't verify a subcontractor with HMRC, calculate a CIS deduction or file the monthly return, it does keep the gross amount, the supplier and the project on every payment line, so the accounting or CIS software that does those things has what it needs when the subcontractor is no longer there to ask. It does nothing about wages, demand or clients who pay late.

What changes when a subcontractor fails

With those controls in place, the over-value application sits in approval instead of the payment run, and the commercial manager values it at what was built before anything is paid. If the firm fails anyway, the job's cost report and the CIS records are already complete, because every line carried the job and the supplier when it was entered. The loss is limited to work certified and not yet delivered, rather than to whatever was paid on trust.

FAQs

Henry Bewicke Author Profile Headshot

The Author:

Henry Bewicke

Having written for clients inluding the World Economic Forum and Harvard University Press, Henry has spent the last six years in the world of b2B SaaS. As Moss's Senior Content Manager he now writes about the tools and trends reshaping how modern finance teams work.

Blog CTA Headshot 1
Blog CTA Headshot 3
Blog CTA Headshot 2

Experience how Moss can help your business

Get a free 15 min demo by a Moss expert

Book an intro

Related Articles