Cash flow is hard to manage in a UK subcontractor or regional contractor because so much of it sits with other people. Each main contractor you work for has its own payment practices and quantity surveyors, and between them they decide when you get paid. Retentions on jobs that finished eighteen months ago are still being held. Meanwhile your own subcontractors and the builders' merchant want paying on the 30th.
The problem has two sides. The money you are owed is controlled by your customers, and will eventually be shaped by legislation now in Parliament. The money you owe is controlled by you. Most of the pain is on the first side, and most of the room to act is on the second. This article looks at where the late payment reforms stand, the payment notice timetable the Construction Act already gives you, why paying your own suppliers late makes things worse, and what finance can control on each side.
Two ledgers, and which one you control
What you are owed, the receivables ledger, depends on your main contractors and, eventually, on legislation. What you owe, the payables ledger, depends on you: when you commit to a supplier, when you pay, and whether you serve your own notices on time.
The receivables ledger causes most of the cash problems, and it is the one you have least control over. The payables ledger is where you have far more say.
The late payment reforms, and where they stand
On 24 March 2026 the government published its response to the late payments consultation. Late payment, it said, costs the UK economy almost £11bn a year and closes 38 businesses every day. The measures it announced were a 60-day cap on payment terms where a large firm pays a smaller supplier, statutory interest at 8% above Bank of England base rate in every commercial contract with no ability to contract out of it, powers for the Small Business Commissioner to investigate, adjudicate and fine persistent late payers, and a requirement for the boards of persistently late-paying large companies to publish an explanation. On retentions, it chose an outright ban on withholding them under construction contracts over the alternative of ring-fencing them, as the simpler option to implement and enforce.
Those measures are now the Commercial Payments Bill. It completed its passage through the House of Lords on 20 October 2026 and is now before the Commons. Royal Assent is expected in 2027, and consultation respondents backed a 12 to 24-month transition for the retention ban.
For your cash flow that means two things. None of it is law yet, so a retention withheld today is withheld under the old rules and governed by your contract and the Construction Act. And the detail can still change in the Commons, so check the Bill's current text before you plan around it.
The notice timetable you can enforce today
While the Bill makes its way through Parliament, the Construction Act already gives you something to enforce. The payer must pay the notified sum unless it serves a valid pay less notice before the deadline. Where the contract is silent, the Statutory Scheme sets the dates: a payment notice within five days of the due date, and a pay less notice no later than seven days before the final date for payment. If the payer misses its own payment notice, you can serve a default notice stating the sum you consider due, and that becomes the sum payable. Contract terms override the Scheme's dates, so the first job is to know which dates apply on each contract.
In practice a payer who has not served a pay less notice in time owes you the sum you applied for, whatever its QS thinks of it. Most finance teams chase by phone; fewer diarise each payer's notice deadlines and treat a missed one as money due.
Why paying your own suppliers late doesn't help
The tempting response to being paid late is to pay late, but there are three ways that goes wrong.
1. As a payer you are bound by the same rules, so a disputed subcontractor sum you did not notify in time is payable in full.
2. Once the Bill is in force, you would be the one owing 8% over base on anything you pay late.
3. The suppliers you squeeze are the ones most likely to fail mid-job, at which point you are re-procuring at this year's prices.
Invoice finance is the other usual answer. It costs margin every month, and lenders tend to exclude retentions, the money outstanding longest.
What finance can control
Your best option is to run the two ledgers on different disciplines.
On the receivables ledger: apply on the contract dates, diarise each payer's notice deadlines, treat a missed notice as an enforceable notified sum, and keep retentions on their own ledger with release dates and the conditions attached. That is credit control and contract administration.
On the payables ledger: approve supplier commitments before they are made, so you know what is coming before the invoice does; pay on a schedule you set rather than as invoices arrive; and serve your own pay less notices on time where a sum is disputed. This is the ledger a finance team owns outright, and it is where a good spend tool pays for itself.
Moss gives you that ledger in one place. Purchase requests put every supplier commitment in front of an approver before it is made, so your committed spend is visible weeks before the invoice lands. Invoices arrive with their due dates captured, route to the right approver automatically, and sit in a payment run you schedule, so the run is a date you set. The result is a payables forecast that reads from commitments rather than guesses, which is exactly what you need when the receivables side is out of your hands.