Finance GuideHow to catch materials budget overruns

Unpredictable materials prices: How to catch budget overruns before the final account

Henry Bewicke Author Profile Headshot
Written byHenry Bewicke
November 11, 2026
Budgeting & Cash Flow5 minutes
What travel finance teams can do about supplier reconciliation

Most contractors find out about materials overruns at the final account, when the job's cost is settled with the client. By then it is months old and there is nothing left to claim.

The reason is simple: the monthly cost report takes its materials figure from the order. A supplier then re-prices mid-job, the later invoice comes in higher, and the invoice is coded to the job and paid. However, because nobody compares the invoice with the order, the report keeps showing the original price, meaning the overrun is invisible until the end.

That ends up costing a job twice. The overrun itself is paid in full and recovered from nobody. And because it was absorbed into contingency rather than traced to a line, the estimator prices the next tender at the old rate.

This article looks at which materials are moving, why the usual fixes leave the gap open, and how two checks, one at the order and one at the invoice, catch the difference the first time it appears.

Which materials are moving

The government's building materials price index puts materials for all construction work up 6.4% in the year to August 2026, the latest month published. The average hides a wide spread. Fabricated structural steel is up 21.2%, rigid pipes and fittings 15.5% and reinforcing bar 12.5%. Ready-mixed concrete, cement and imported sawn timber are flat or slightly down. In 2026, the biggest moves are mostly in steel.

Why the usual fixes leave the gap open

Each of the typical responses teams reach for tends to fall short:

1. Fixing prices with suppliers works for the lines a supplier will hold, but they won't be able to hold a 21% move in steel for long.

2. Buying early ties up cash the job doesn't have.

3. Reporting more often doesn't help if the report still takes its number from the order.

4. A contingency in the tender absorbs the overrun, which is exactly why the next tender inherits the old rate.

None of these puts the invoice next to the order.

Timing matters as well. Under the Construction Act, you have a fixed window to serve a pay less notice on a supplier; miss it and the invoice becomes the sum due. And whether you can pass any increase on to the client depends on the contract, usually through a fluctuations clause or a client-caused delay, and the claim has to go in before that valuation closes. In both cases the deadline falls soon after the invoice arrives, but by the final account both have passed.

Two checks that catch it early

To catch overruns you have to check the commitment at both ends, meaning before the order and after delivery.

Before the order: the purchase request is approved against the project budget, so the commitment is on record at a figure the job can carry.

After delivery: every invoice is matched to its order with no tolerance. Any difference between what was ordered and what was invoiced becomes something a person has to approve, with the project and supplier attached.

That moves the discovery from the final account to the first invoice that disagrees. What to do about it, whether to challenge the supplier, re-quote, claim from the client or absorb it, stays a commercial decision.

How Moss does it

In Moss, a materials package starts as a purchase request, routed to an approver with the project and budget it will be charged to. Once approved it becomes a purchase order with a PO number the supplier quotes back. Until the invoice arrives, finance can see at any point what is on order and not yet invoiced.

When the invoice comes in, Moss links it to the order by the PO number and checks the amount. At or below the order value, it goes through. Over it by any amount, it goes back to an approver. There is no tolerance band, so a small delivery charge stops an invoice as surely as a re-priced frame does. That is deliberate: the alternative is deciding in advance which overruns don't matter. For goods, the site team can record what was delivered as a goods received note, so the invoice is also matched against what arrived.

While Moss can't forecast steel, index-link contracts, hedge or negotiate with suppliers, it does show the gap between the price committed and the price charged on the first invoice that carries it, with the project code and the original order beside it. The price itself stays procurement's job.

What changes

With a check at the order and a check at the invoice, an invoice that comes in over its order now sits in approval rather than in the payment run. The commercial manager checks whether the contract lets any of the increase through to the client and, if it does, puts it in the next application. If it doesn't, the job absorbs it now, with the figure known. Either way the overrun sits against a named line and a named supplier, so the next tender prices the material at what it actually cost.

To see how this works in practice, the help centre's purchase request overview walks through the lifecycle from request to matched invoice.

FAQs

Henry Bewicke Author Profile Headshot

The Author:

Henry Bewicke

Having written for clients inluding the World Economic Forum and Harvard University Press, Henry has spent the last six years in the world of b2B SaaS. As Moss's Senior Content Manager he now writes about the tools and trends reshaping how modern finance teams work.

Blog CTA Headshot 1
Blog CTA Headshot 3
Blog CTA Headshot 2

Experience how Moss can help your business

Get a free 15 min demo by a Moss expert

Book an intro

Related Articles